T2 Key Facts
Size: 75,000 sq metres
Cost: €395m
Capacity: Up to 15 million
passengers per year
Location: Close to the roundabout on the approach road to
the existing terminal
Check-in desks: 58 traditional desks, also ample
provision for self-service check-in and bag drop positions
Retail space:
9,000 sq metres
Planning application lodged: August 2006
Construction
projected to begin: 2nd quarter 2007
Opening in: Autumn 2009
Scalable:
Planning application provides for a second phase of 15,000 sq metres that can be
added at a later date
Pier E Key Facts
Size: 24,000 sq metres
Space for: Up to 19 aircraft (19 short-haul
or eight long haul)
Other Enhancements
Improved campus road network
Dedicated approach roads for T1 &
T2
Major utilities upgrade
Locations provided for future Metro and Ground
Transportation Centre